Construction is progressing strongly across both the live/work and commercial components of the development, with significant structural milestones now achieved.
On the live/work side, mid-floor framing is complete, marking a major step forward in the vertical build. We have also commenced apartment internal framing, with initial partition walls now installed. Internal concrete panels have been placed, further defining the layout.
Steel portals have been installed in preparation for the brick façade, ensuring the exterior architectural elements can proceed as scheduled.
On the commercial and retail side, the roof has now been installed, providing full weather protection to this portion of the building. Ground floor framing to the office areas is underway, followed by installation of the mezzanine level within the retail space.
Key Milestones Achieved
-
Completion of earthworks and structural steel in preparation for tilt slab installation
-
Underslab plumbing and drainage completed prior to foundation pours
-
Concrete foundations poured across the development
-
Installation of 6-metre-high tilt slabs
-
Progression of steel trusses to the commercial retail side
-
Roof installation to the commercial retail building
-
Delivery and installation of mid-floor timber framing to the live/work side
-
Installation of steel portals to support the brick façade
What’s Next
Over the coming weeks, works will continue on:
-
Completion of apartment internal framing
-
Installation of the commercial mezzanine structure
-
Continued façade preparation and external works
The development remains on schedule, with steady progress across all areas of the site.